INSTALLATION
Vecto r H® S eries Operat ors M anual M N-46 2 95 Rev 7 6/22
35
Continued from previous page
Level the oven To level the oven, do the following.
3. Check the level of the oven using a spirit (bubble) level. Check front to back
and side to side.
Adjust the legs, if necessary, to achieve levelness.
The oven is now level.
Connect the wiring
To connect the wiring, do the following.
4. Remove the top cover a.
Continued on next page
VMC-TS-007501
WARNING: Electric shock hazard.
Make sure the supply cord is not connected to a
power supply.
VMC-TS-007943
a

Table of Contents