Step 8
Connecting APsystems microinverters to the grid
a. Please install bi-polar circuit breakers with the appropriate rated current or according to local regulations.
These circuit breakers are mandatory for grid connection.
Step 9
AC extension cable
When an AC extension cable is required, users can either connect the AC bus cable and AC extension
accessories.
Step 10
Completing the APsystems installation map
a. Each APsystems Microinverter comes with 2 removable serial number labels.
b. Complete the installation map by affixing the ID label of each microinverter at the appropriate location.
c. The second serial number label can be adhered to the solar module frame. This label will assist in later
confirmation of the microinverter's position without the need to dismantle the PV module.
NOTE:
installations.
numbers on the map (refer to the ECU instruction manual for further details).
OR
AC Extension Cable
AC Junction Box
Bus Cable End Cap
We, ALTENERGY POWER SYSTEM INC.
Of
Building 2, No. 522, Yatai Road, Nanhu District, Jiaxing City, Zhejiang 314050, China declare under our sole responsibility that the product
Product Description: Grid-tied Microinverter
Model No.: QT2, QT2-EU
Safety
Health
EMC
Radio
We hereby declare that all essential radio test suites have been carried out and that the above named product is conformity to all the essential requirements of
EU DECLARATION OF CONFORMITY
Title: Director
Address: Jiaxing, China