EasyManuals Logo

Ariel JGQ User Manual

Default Icon
178 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #50 background imageLoading...
Page #50 background image
FOR MODELS: JGI, JGM, JGN, JGP AND JGQ SECTION 3 - START UP
PAGE 3-4 9/08
START-UP CHECK LIST - ITEMS TO CHECK IN THE FIELD AT COMMISSIONING
Description Date Checked Date Verified
1. Check and verify the top cover data plate of the compres-
sor frame for compressor design limitations such as rod
load, maximum and minimum speed, and maximum lube
oil temperature.
Commissioning Agent:
__________________
Distributor:___________
2. Check and verify the availability of correct start-up spares,
hand tools, special tools, compressor parts list and draw-
ings, and technical manuals at installation.
Commissioning Agent:
__________________
Distributor:___________
3. Check and verify the Ariel lube sheet and Lubrication
Specification matches the recommended oil grade and vis-
cosity for the service.
Commissioning Agent:
__________________
Distributor:___________
4. Check and verify all lube oil piping cleanliness per Ariel
lubrication specifications (see Technical Manual, Section
4).
Commissioning Agent:
__________________
Distributor:___________
5. Verify lube oil storage and supply line cleanliness per ER-
56.06. Verify crankcase oil supply isolation valve is open.
Commissioning Agent:
__________________
Distributor:___________
6. Verify prelube piping cleanliness per ER-56.06 and correct
circuit operation.
Commissioning Agent:
__________________
Distributor:___________
7. Verify there is an oil cooler and high temperature shut-
down for the oil into the compressor frame.
Commissioning Agent:
__________________
Distributor:___________
8. Verify whether the temperature control valve installation is
blending or diverting (blending preferred). _____________
Commissioning Agent:
__________________
Distributor:___________
9. Check compressor crankcase oil level controller for proper
installation, operation, levelness, and venting.
Commissioning Agent:
__________________
Distributor:___________
10. If applicable, check cooling water circuit cleanliness for the
oil cooler and cooled packing per Technical Manual. Verify
correct routing and test pump rotation. Set pressure appro-
priately per Technical Manual and leak test.
Commissioning Agent:
__________________
Distributor:___________
11. Verify correct filter element installation. Prime the oil filter
element and all lube oil piping with oil.
Commissioning Agent:
__________________
Distributor:___________
12. Verify proper compressor crankcase oil level before start-
ing (about 7/8 full in site glass).
Commissioning Agent:
__________________
Distributor:___________
13. Verify correct installation of a low oil pressure shutdown
tubed to the downstream side of the oil filter.
Commissioning Agent:
__________________
Distributor:___________
14. Operate pre-lube system.
Commissioning Agent:
__________________
Distributor:___________
15. OPTIONAL STEP: Record “out of plane” readings (pre-grout) - see ER-82.
Drive End _________ _________ _________ _________ _________ _________ Auxiliary End
_________ _________ _________ _________ _________ _________
Commissioning Agent:
__________________
Distributor:___________
16. Record soft foot readings. More than 0.002 inches (0.05 mm) pull-down on any frame foot requires cor-
rection. See Technical Manual.
Drive End _________ _________ _________ _________ _________ _________ Auxiliary End
_________ _________ _________ _________ _________ _________
Commissioning Agent:
__________________
Distributor:___________

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Ariel JGQ and is the answer not in the manual?

Ariel JGQ Specifications

General IconGeneral
BrandAriel
ModelJGQ
CategoryAir Compressor
LanguageEnglish

Related product manuals