FOR MODELS: JGI, JGM, JGN, JGP AND JGQ SECTION 3 - START UP
9/08 PAGE 3-9
8. Check and verify distribution block cycle time indicator and
set lubricator pump for proper break-in rate.
Commissioning Agent:
__________________
Distributor:___________
9. Check and verify the unit and piping is free from any gas or
fluid leaks. Record any occurrences.
________________________________________
________________________________________
________________________________________
________________________________________
Commissioning Agent:
__________________
Distributor:___________
10. Check and verify scrubber high level shutdowns operation
and check scrubber dumps operation and frequency.
Commissioning Agent:
__________________
Distributor:___________
11. Check, verify, and record tank levels that indicate the
amount of liquids removed from the gas.
__________________________
Commissioning Agent:
__________________
Distributor:___________
12. Check and verify piston rod packings seal properly in the
primary packing vents.
Commissioning Agent:
__________________
Distributor:___________
13. Check and verify operation of all safety functions to ensure
unit shutdown upon indication.
Commissioning Agent:
__________________
Distributor:___________
14. If applicable, check and verify main bearing temperatures
and record. Watch for even bearing temperature increase.
Commissioning Agent:
__________________
Distributor:___________
15. During various operational conditions, use the Ariel perfor-
mance program to check and verify operational character-
istics of various load steps.
Commissioning Agent:
__________________
Distributor:___________