commissioning
29
First ignition operation
1. Check the electrical supply.
Complete . . . . . .
Date . . . . . . . . . . . .
Installer . . . . . . . . . .
2. Check the type of gas and
change the gas if necessary.
Complete . . . . . .
3. Check the gas tightness.
Complete . . . . . .
5. Check the exhaust  ue.
See page 18
Complete . . . . . .
6. Fill the installation.
See page 30
Complete . . . . . .
7. Check the hydraulic water
tightness.
Complete . . . . . .
8. Spin the pump.
Complete . . . . . .
9. Set the heating power.
See page 31
Complete . . . . . .
10. Set up heating controls
Complete . . . . . .
11. Balance the central heating
circuit.
Complete . . . . . .
12. Check the boiler in DHW mode
(combi only)
Complete . . . . . .
13. Adjust DHW  ow rate on the
boiler (if necessary).
Complete . . . . . .
14. Analyse the combustion
(see page 33)
Complete . . . . . .
15. Check the ionisation current.
Complete . . . . . .
16. Explain to the end user the the
boiler operation.
Complete . . . . . .
17. At the time of commissioning, complete all relevant sections of the
Benchmark Checklist located on the inside back pages of this document.
Complete . . . . . .
6. Measure the gas inlet pressure.
standing + warming pressure
Complete . . . . . .