Armstrong EHU-804 - Start Up Checklist; Pre Start Up Inspection Items

Armstrong EHU-804
60 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
North America • Latin America • India • Europe / Middle East / Africa • China • Pacific Rim
armstronginternational.com
Designs, materials, weights and performance ratings are approximate and subject to change without notice. Visit armstronginternational.com for up-to-date information.
46
Start Up Checklist
Armstrong EHU-800 Series Pre Start Up Checklist
Humidifier Model: ____________________ Serial #: ____________________
Voltage: ____________________ ph: ____________________ KW: ____________________
Steam Capacity: ____________________ lbs/hr
Job Name: ____________________________________________________________
Unit Tag: ____________________
Inspected by: ____________________ Date: _____/_____/______
Water Type:
Tap Water Connectivity: ____________________ µMhos/cm
Blended Conductivity: ____________________ µMhos/cm
Humidifier Mounting:
Clearance needed:
Left side (4”) Obstruction: ________________________________________
Right side (24”) Obstruction: ________________________________________
Front (24”) Obstruction: ________________________________________
Bottom (12”) Obstruction: ________________________________________
Steam Dispersion Piping:
Copper Stainless Steel Hose
Size:_______ Insulated
Length:_______
Number of elbows:
45° Elbows:_______
90° Elbows:_______
Slope up 1” per 12” Sloped back to drain
Slope down 1” per 12”
P-trap at bottom of every vertical down run P-trap Height: _______”
P-trap every 20 equivalent feet of dispersion piping P-trap Height: _______”