Procedure
1. If installed, close the dryer by-pass valve. See Installation proposal.
2. Press dryer on/off switch (2).
3. Open dryer air inlet valve (customer's installation).
4. Approx. 5 minutes later, open dryer air outlet valve (customer's installation).
5. Approx. 10 minutes later, the nominal dewpoint will be reached.
5.4 During operation
Procedure
Regularly check:
• The pressure dewpoint indicator (1) on the control panel. The pressure dewpoint will deviate
from nominal value if air inlet conditions or volume flow differ from nominal value.
• That condensate is discharged via condensate outlet. The amount depends on the operating
conditions.
5.5 Stopping
Attention
Warning:
To ensure optimum operational efficiency, do not use dryer on/off switch repeatedly within a
short time period.
Wait at least 5 minutes to start the dryer again after stopping to allow pressure equalization.
Instruction book
24 2920 7210 40