Issue 8 January 2008 3
Process and Specifications
1 Verifying the Equipment
2 Installing the SNMP Module in the UPS
3 Installing the Optional Second Hard Drive
4 Installing the DAL2 Card
5 Installing the Hardware in the Rack
6 Connecting the Cables
7 Configuring the UPS and the Ethernet Switch
8 Connecting the Laptop
9 Connecting to the G650 Media Gateway
10 Troubleshooting
Hardware Specifications
Weight Dimensions
Equipment English (lb) Metric (kg) English (in) Metric (cm) Us
S8730, S8720, or
S8710 Server
60 27 3.4 x 17.5 x 26 8.6 x 45 x 66 2
UPS >34 >15 3.5 x 17 x 19 9 x 43 x 48 2
Ethernet switch
C363T
C364T
11
11
5
5
1.75 x 17 x 14.5
1.75 x 17 x 14.5
4.5 x 43 x 36.5
4.5 x 43 x 36.5
1
1