Start-up
VAS 6910 Unpacking Instructions, Start-up, Brief instructions V9.00 10/17 All rights reserved.
447 232 00 00
4-2
4.2 Hardware
CAUTION
Temperature compensation
When delivering the VAS 6910 in the winter, the inside of the device must be prevented
from becoming moist. For this reason, we request that you allow the device to stand for
approx. 3 hours at the location from which it is to be operated before connecting it or
switching it on!
CAUTION
Before using the VAS 6910, read through the operating manuals.
They contain additional information on starting-up and operation..
WARNING
Set up the VAS 6910 so that adequate ventilation is guaranteed, fans and air vents are
not obstructed and the air must circulate freely!
Set up the VAS 6910 in a way that there is always free access to the power separator!
(Power cord from the mains socket).
1. Open the latches (1), (2), (4) and (5) and remove the cover (3).
Fig. 4-1 VAS 6910
1 2
5 4
3

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the AVL DITEST VAS 6910 and is the answer not in the manual?

AVL DITEST VAS 6910 Specifications

General IconGeneral
BrandAVL DITEST
ModelVAS 6910
CategoryService Equipment
LanguageEnglish

Related product manuals