EasyManuals Logo

Bartec PSB User Manual

Bartec PSB
46 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #19 background imageLoading...
Page #19 background image
21-1S00-7D0001/-
05/2023-EHT-466853
Notice Technical data subject to change without notice.
No claims for damage arising from alternations, errors or misprints shall be allowed.
Page 17 / 42
Step 8: Determine the required allowance for pumps, valves, flanges and pipe supports:
Determine the required allowances for pumps, valves, flanges and pipe supports using the following table:
Table F: Allowance values and pipe support intervals
Pipe diameter
in DN / inch
DN8
1/4"
DN15
1/2"
DN20
3/4"
DN25
1"
DN32
11/4"
DN40
11/2"
DN50
2"
DN65
21/2"
DN80
3"
DN100
4"
DN150
6"
DN200
8"
DN250
10"
DN300
12"
Allowance for pumps
in m
1.5
2
2
2.1
2.3
2.3
2.4
2.4
2.4
2.6
3
3.5
4
4
Allowance for valves
in m
0.5
0.5
0.5
0.6
0.6
0.7
0.7
1
1
1.3
1.5
1.6
1.8
2
Allowance for flanges
in m
0.2
0.2
0.3
0.3
0.3
0.3
0.4
0.4
0.5
0.7
0.9
1
1.2
1.2
Allowance for pipe supports
in m
0.2
0.2
0.3
0.3
0.3
0.3
0.4
0.4
0.5
0.7
0.9
1
1.2
1.2
Typical pipe support interval
in m
1
1.5
1.5
2
2
2.5
3.1
4
4
5
6
7
8
8
Example
Pipe diameter: DN25
1 pump
2 valves
6 flanges
24 pipe supports
The total required allowance is calculated as follows:
total required allowance = no. of pumps × pump allowance value +
no. of valves × valve allowance value +
no. of flanges × flange allowance value +
no. of pipe supports × pipe support allowance value
= 1 × 2.1 m + 2 × 0.6 m + 6 × 0.3 m + 24 × 0.3 m
= 12.3 m
Step 9: Add all lengths / allowances together:
Add the lengths for piping (as determined in step 6) and allowances (as determined in step 7 and step 8) together to obtain total required trace
heater length.
Example
required trace heater length for piping (step 6): 50 m
required allowances for connection kits (step 7): 1.0 m
required allowances for pumps, valves, flanges and pipe supports (step 8): 12.3 m
total required trace heater length = required trace heater length for piping + required allowances
= 50 m + 1.0 m + 12.3 m
= 63.3 m
Determination of the required number of heating circuits
Step 10: Confirm the number of electrical circuits required for the application:
Using Table G on page 18, compare the required heater length and start up temperature to the available circuit breaker allowances to determine
the number of electrical circuits that will be required.
Example
total required trace heater length: 63.3 m
circuit breaker voltage: 230 Vac
selected trace heater: 10 PSB
circuit breaker amperage: 25 A
required start-up temperature: -20 °C
allowable trace heater length from table below = maximum of 69 m at -20 °C on 25 A circuit breaker at 230 Vac
= 63.3 m calculated < 69 m maximum allowable for 25 A = 1 circuit

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Bartec PSB and is the answer not in the manual?

Bartec PSB Specifications

General IconGeneral
BrandBartec
ModelPSB
CategoryHeating System
LanguageEnglish