14
4.10 Installing the auxiliary parts
Install the plastic cover (PV) to EP600 and install the plastic cover (AC, with label) to EP600.
4.11 Connecting to the main panel
4.11.1 Find out the essential household appliances
NOTE:
Before installing the EP600 energy storage system, you should consider whether to
make a partial backup system. If there is a lot of power outage, you need to build a
backup system.
Please make sure the total rated power of the essential appliances connected to the
BACKUP of EP600 such as the fridge and lights is less than 2000W each phase, in case
three phase is less than 6000W.
NOTE: Other high-power appliances must be connected to the public grid.
4.11.2 Create a plan for the essential backup appliances
Before installing EP600 energy storage system, please create a plan for the essential
appliances such as the refrigerator and lights . EP600 can output rated 2000VA each phase
or three phase 6000VA. Please allocate the circuit breakers to your residential essential
appliances.
Load Balancing Example:
Circuit Breaker Connections: Three 230 V single pole circuit breakers, or one three pole circuit breakers
Total Running
Watts Phase
One:
Total Running
Watts Phase
two:
Total Running
Watts Phase
three:
Total essential Running Watts Phase One: <2000W,
Total Running Watts Phase Two: <2000W,
Total Running Watts Phase Three: <2000W,
It’s OK!