4.11.5 Installing the CT to grid power cables.
The arrow inside the CT points to the grid.
Pay attention to the phase sequence.
L1 to R, L2 to S, L3 to T
4.11.6 Turn on the transfer switch
Step 1 Turn the transfer switch to position II. The current flows from the Grid to the loads.