7.12.1 Initial Start-up
• Make sure that power connections of the circulation pipe have been made as specified in the
manufacturer firm’s user manual.
• Make sure that the water supply valve is in the open, the water overflow valve is in the open, the
water draining valve is in the closed, and the pump cut-off valves are in the open positions.
• Make sure that the float valve system is operational.
• Make sure that the installation line to which the water overflow is connected is operational.
• Power the pump and check the direction of rotation against the label indicating the direction of
rotation. If the direction is incorrect, reverse electrical connection terminals.
• Make sure there are no water leakages in the installation after initial start-up.
• Make sure that wick surfaces are evenly moistened. Otherwise, notify the BOREAS A.Ş. Technical
Service Department.
7.12.2 Maintenance
It is recommended that maintenance procedures be carried out every month. These maintenance
procedures are important since they affect the unit’s capacity for humidification.
7.13 HIGH PRESSURE HUMIDIFIER SYSTEM
All provisions stated under the heading of 2. GENERAL SAFETY must be applied during the
commissioning and maintenance of the high pressure humidifier system.
Properties of the circulation water that should be used in the system have been provided in Table 3.
7.13.1 Initial Start-up
• Make sure that the pan within the section is clean.
• Care must be taken to ensure that there are no metal shavings within the section. Any metal
shavings will lead to rapid corrosion.
• Make sure that the valves on the supply line are open.
Periodical Maintenance on the Evaporative Humidifier System:
• Make sure that wick surfaces are evenly moistened.
• Check for any odours within the section. If odour is present, the wicks should be replaced.
Notify the BOREAS A.Ş. Technical Service Department.
• Check the installation for leaks.
• Make sure that drainage lines are functional.