6 720 817 545 (2016/02)Optiflow
Installation (only by authorised technicians) | 11
housing.
Ensure this intake is free from vegetation and other
obstructions.
In order to prevent corrosion, the combustion air must not
contain any corrosive substances.
Substances classed as corrosion-promoting include
halogenated hydrocarbons containing chlorine and fluorine
compounds. They may be found in solvents, paints, adhesives,
aerosol propellants and household cleaners.
If these conditions cannot be guaranteed, a different site must
be chosen for the appliance.
Surface temperature
The maximum surface temperature of the appliance is below
85 °C. No special safety precautions are required with regard
to flammable building materials.
Ensure local building codes and regulations are followed.
4.2 Minimum clearances
Install the appliance in accordance with the minimum
installation clearances indicated in Fig. 5 and Table 6,
according to AS/NZS5601.
The appliance must not be installed over a heat source.
Do not obstruct the openings of appliance.
The appliance must installed in a position that is easily
accessible to allow service work. It is recommended the
appliance is installed no more than 2m from the ground to
the base of the appliance.
The areas 30cms above and below the appliance must be
clear of obstacles.
Fig. 5 Minimum flue clearances
4.3 Installing the appliance
Remove the appliance from the packaging.
Check that all the items indicated are included
(section 2.3).
Remove the covers from the gas and water connections.
Check that the gas type available matches that shown on
the sticker on the front of appliance, and on its dataplate.
6720817545-09.2V
N
C
J
B
J
A
C
A
K
G
A
H
N
F
J
A
C
K
B
B
B
G
K
H
Flue terminal positions
for water heaters in accordance
with AS/NZ5601
D
D
GM
P
K
E
E
Item Min.clea-
rance (mm)
A Below eaves, balconies and other
projections
300
B From the ground, above a balcony or other
surface
1)
1) unless appliance is certified for closer installation
300
C From a return wall or external corner
1)
300
D From a gas meter (GM) 1000
E From an electricity meter or fuse box (P)
2)
2) Prohibited area below electricity meter or fuse box extends
to ground level
500
F From a drain pipe or soil pipe 75
G Horizontally from any building structure
1)
or obstruction facing a terminal
500
H From any other flue terminal, cowl, or
combustion air intake
1)
300
J Horizontally from an openable window, door, non-
mechanical air inlet, or any other opening into a building
with the exception of sub-floor ventilation:
Appliances up to 150 MJ/h input
1)
300
Appliances over 150 MJ/h input up to 200
MJ/h input
1)
300
K From a mechanical air inlet, including a spa
blower
1000
N Vertically below an openable window, non-mechanical air
inlet, or any other opening into a building with the
exception of sub-floor ventilation:
Appliances over 50 MJ/h input and up to
150 MJ/h input
1000
Appliances over 150 MJ/h input 1500
Table 6
NOTICE: The appliance may be damaged if
dirt is allowed to enter via the gas or water
connections.
Purge the pipes to eliminate
possible foreign bodies.