5.4 PLACING INTO OPERATION:
Before commencing to test your Alarm 2000 system, it is important to ensure that the
equipment interfaced to the system e.g. Sprinkler system, Gas Supply or Air-conditioning,
has been isolated using the suitable isolate facility either in the panel or on the equipment
itself. It is also important to notify the occupants and the monitoring centre if the system is
monitored. The following check procedures are recommended following each installation.
Initial Check List:
A visual inspection should be performed to the system to ensure no physical damage or
loose wires or components inside the enclosure.
Cabinet visual check
Viewing window clear and firmly secured
All boards firmly mounted
DIP Switch correctly set
Optional modules as per client order
Mains Smoke/Heat Alarms wiring correctly terminated
All 230V
AC
mains cables correctly terminated
All ribbon Cables firmly secured
EOL resistors & diodes correctly terminated on the field devices
Manuals and instructions supplied
Power up Check List:
Ensure Key switch in the OFF position
Turn ON the mains isolating switch
Main on LED illuminates
Connect batteries
Place the Key switch in the AUTO position
Ensure all LEDs are OFF’ except Mains on LED
Ensure no Smoke / Heat Alarm is sounding
Check charger output voltage 27.3V DC