INSTALLATION START-UP REQUEST CHECKLIST
Machine Model Number: __________________________________  19XR Serial Number:
To:
Date   
Attn:  
 
Project Name
 
Carrier Job Number
NOTE: For units with medium voltage freestanding VFD, consult latest pre-commissioning Rockwell Powerflex 7000 checklist for the applicable
VFD frame size. The checklist is available at http://www.literature.rockwellautomation.com.
The following information provides the status of the chiller installation.
YES/NO DATE TO BE
(N/A) COMPLETED
1. The machine is level.
2. The machine components are installed and connected in
accordance with the installation instructions.
3. The isolation package and grouting (if necessary)
are installed.
4. The relief valves are piped to the atmosphere.
5. All piping is installed and supported. Direction of flow
is indicated in accordance with the installation instructions
and job prints.
a. Chilled water piping
b. Condenser water piping
c. Waterbox drain piping
d. Pumpout unit condenser piping (if installed)
e. Other 
6. Gages are installed as called for on the job prints required
to establish design flow for the cooler and condenser.
a. Water pressure gages IN and OUT
b. Water temperature gages IN and OUT
NOTE:  To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices and adhere to
the safety considerations/information as outlined in preceding sec-
tions of this Installation Instructions document.