Upon building pressure, the compressor is allowed to start
(after 15 seconds). For across-the-line (XL) start chillers, the
compressor starts and comes up to full speed within 1 to 3 sec-
onds. For Wye-Delta start chillers, contactors 1M and S (starter
contactor assembly) are closed and the compressor is started in
a Wye configuration. This method reduces the locked rotor
current requirements by approximately 60% while maintaining
enough torque to bring the compressor up to full speed.
FIELD WIRING
Field wiring is shown in Fig. 40-54.
LEGEND FOR FIG. 40-54
* Dependant on control circuit power supply voltage.
ALM Alarm
CFR Condenser Fan Relay
CMP Chiller Water Pump
CNFS Condenser Flow Switch
CNPI Condenser Pump Interlock
CNP-R Condenser Pump Relay
CWP Chilled Water Pump
EMM Energy Management Module
EWT Entering Water Thermistor
FIOP Factory-Installed Option
FSR Flow Switch Relay
FU Fuse
GFI-CO Ground Fault Interrupter Convenience Outlet
GND Ground
LLSV Liquid Line Solenoid Valve
LWT Leaving Water Thermistor
MBB Main Base Board
MLV Minimum Load Valve
NEC National Electrical Code
OAT Outdoor-Air Thermistor
SCB Screw Compressor Board
SPT Space Temperature Sensor
SW Switch
TB Terminal Block
Field-Wired
Factory Wired
FIELD CONTROL POWER SUPPLY
NEC FUSED DISCONNECT
230 V CONTROL CIRCUITS
USE 15 AMP MAXIMUM FROM
SEPARATE POWER SUPPLY
115 V CONTROL CIRCUITS
USE 30 AMP MAXIMUM FROM
SEPARATE POWER SUPPLY
2
1
GND
TB4
Fig. 40 Power Supply Wiring
MBB
MBB
Fig. 41 Remote Alarm Relay Accessory Wiring; All Models, 115 or 230 V*
Fig. 42 Chilled Water Pump Relay Wiring; All Models, 115 or 230 V*
Fig. 43 Optional Ground Fault Interrupter; Convenience Outlet Accessory Wiring