Test Operation ESIE09-08A
78 Test Operation
1. Test Operation
1.1 Procedure and Outline
Follow the following procedure to conduct the initial test operation after installation.
1.1.1 Check Work Prior to Turn Power Supply On
Check on refrigerant piping
(V3180)
Check on amount of refrigerant
charge
Check air tight test and vacuum
drying
Check on water piping
Check the below items.
Power wiring
Control transmission wiring
between units
Earth wire

Table of Contents