D4-9 / D4-9X Four-Post Lifts 12 P/N 5900251Rev. A1August 2021
Installation Checklist
Following are the steps needed to install your Lift. Perform them in the order shown.
1. Review the installation safety rules.
2. Make sure you have the necessary tools.
3. Check for clearances around the Lift.
4. About the usable area of the Lift.
5. Select the Lift location.
6. Plan for electrical work.
7. Unload and unpack the Lift components.
8. Choose the Power Post location.
9. Understand the orientation issues.
10. Create Chalk Line guides.
11. Move the Posts into position.
12. Install the Crosstubes.
13. Raise the Crosstubes.
14. Install the Runways.
15. Learn about Safety Locks.
16. Install the Safety Lock Release Mechanism.
17. Learn about the Pivot Pieces
18. Install the Top Caps.
19. About Cables Sheaves.
20. Lubricate the Cable Sheaves
21. Route the Lifting Cables.
22. Install the Power Unit.
23. Install the Flex Tube.
24. Learn about Hydraulic Fluid Contamination and Liquid Thread Sealant.
25. Install the Flex Tube.
26. Install the Hydraulic Hoses.
27. Install the Return Line.
28. About Compression Fittings and Tubing.
29. Contact the Electrician.
30. Connect to a power source (
Electrician required for 220 VAC operation
).
31. Install the Power Disconnect Switch and Thermal Disconnect Switch (
Electrician required
).
32. Add Hydraulic Fluid to the Power Unit reservoir.
33. About Embedment.
34. Anchor the Posts.
35. Perform final leveling.
36. Install the accessories.
37. Perform an operational test.
38. Review the final checklist.