EasyManua.ls Logo

Dell EMC PowerMax Series - Procedure A, Task 2: Dell EMC Customer Engineer

Dell EMC PowerMax Series
71 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Customer’s
PDU 1
Customer’s
PDU 2
Circuit
breaker
off (0)
Circuit
breaker
off (0)
Circuit breakers - Numbers
27
28
29
30
Circuit breakers - Numbers
...
8
9
10
11
...
PDU 2
CB 9
PDU 1
CB 28
Labels on
customer
power lines
Voltmeter
TYPE PM89
CLASS 25 01
0
100
240
300
V
Voltmeter
TYPE PM89
CLASS 25 01
0
100
240
300
V
Figure 29. Circuit breakers OFF — No AC power
Procedure A, Task 2: Dell EMC Customer Engineer
Before connecting power to the PowerMax system, make sure that the power for both zone A and zone B are turned OFF. This task is
performed by the Dell EMC Customer Engineer.
NOTE: Do not connect storage bay power zone A and power zone B to the same customer-supplied PDU. The customer
will lose power redundancy and risk Data Unavailability (DU) if the PDU fails or is turned off during a maintenance
procedure.
64 Best Practices for AC Power Connections