8 Rack Installation Guide
Figure 1-1. Rack Kit Contents
Installation Tasks
Installing a rack kit involves performing the following tasks (described in detail in subsequent sections)
in their numbered order:
1
Removing the rack doors
2
Marking the rack
3
Configuring the sliding rail assemblies
4
Installing the mounting rails in the rack
RapidRails installation
VersaRails installation
5
Installing the system in the rack
6
Installing the cable-management arm
7
Routing cables
8
Attaching the cable-management arm ramp assembly
9
Replacing the rack doors
1 cable-management arm 2 left cable-management arm
ramp assembly
3 right cable-management arm
ramp assembly
4 slide assemblies 5 10-32 x 0.5-inch flange-head
Phillips screws (8)
6 status indicator cable
(if applicable)
5
1
6
4
2
3