Service - 134 RT80 Operator’s Manual
As Needed
To install chain:
1. Lay chain on ground with teeth down and pointed toward unit.
2. Fasten and adjust seatbelt.
3. Start tractor. See page 62 for start-up procedures.
4. Disengage parking brake and verify parking brake indicator is off.
5. Move ground drive control to reverse.
6. Back unit up until chain extends past head shaft about 1’ (305 mm).
7. Move ground drive control to neutral.
8. Lower backfill blade to ground.
9. Lower boom to horizontal position.
10. Engage parking brake and verify parking brake indicator is on.
11. Turn ignition switch to STOP.
12. Pull rear end of chain over and about 10" (260 mm) past tail roller.
13. Use hoist to pull front end of chain over head shaft sprocket.
14. Move chain down boom until chain connector pin and lock key can be installed. Install connector pin
and lock key.
15. Tighten chain by pumping EPG into grease cylinder.
Time Augers
Ensure that augers are balanced, as shown. If auger
timing is off, unit will bounce from side to side even in
normal digging conditions.
To adjust timing:
1. Remove bolts holding augers to auger shaft and
rotate either auger as needed until augers are
balanced.
2. Reinstall bolts and tighten securely.
t12om081h.eps

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Ditch Witch RT80 and is the answer not in the manual?

Ditch Witch RT80 Specifications

General IconGeneral
BrandDitch Witch
ModelRT80
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals