ote: N If concentric neutral cable is not being used,
follow cable preparation directions in shield
adapter kit.
Equipment provided
BT-TAP Connector assembly kit includes:
T-body
Cable adapter
BT-TAP Loadbreak reducing tap plug (BLRTP)
Threaded Stud
200 A Loadbreak protective cap (when furnished)
Shear bolt connector
Silicone lubricant
Instruction sheet
Tools required
Torque wrench
5/16” Hex wrench for splice application
Cable stripping tools
5 mm or 8 mm Allen wrench
Installation of connectors
Shear bolt installation procedure
(For compression connector procedures, see page 7)
Prepare the cable
Step 1.
Train cable
Position cable vertically so that it is centered between
apparatus bushing and parking pocket, parallel to, and 6”
(152 mm) from apparatus frontplate.
Provide adequate cable slack for cable movement
between standoff bushing and apparatus bushing.
Support cable as needed to maintain position.
Cut cable to length A” from centerline of bushing. (Refer
to Figure 3 and Table 2 for A” length.
Installation Instructions to be used for 600 A, 15 and 25 kV
Class BT-TAP connector with shear bolt connector. Please
see page 7 for installation instructions using a compression
connector.
B
C
D A
Figure 2. Strip back dimensions.
Figure 3. Line illustration for cable training.
Bushing
Cable
"A"
(See Table 1)
6"
(152 mm)
IMPORTANT
2
600 A 15 kV and 25 kV class BT-TAP connector system installation instructions MN650004EN May 2021
Catalog data MN650004EN
Effective May 2021