8
ETL Model No.: CF955L
HANGER BALL/
DOWNROD
ASSEMBLY
HANGER BALL
WHITE WIRE
BLACK WIRE
1/2-INCH
DOWNROD
6 TO 9
INCHES
Figure 10
3.10
The fan comes with black and white leads that are
80long.
Measure up approximately 6 to 9-inches above top of
hanger ball / downrod assembly (Figure 10).
Cut off excess leads and strip back insulation 1/2-inch from
end of leads.
Carefully turn the partially assembled ceiling fan upside
down and place onto the foam pad in preparation for
mounting the fan blades and light fixture.
HANGER
BALL
CEILING
COVER
DOWNROD
PIN
SET SCREW
Figure 9
3.9
Reinstall the hanger ball (Figure 9) on the downrod as
follows:
Route the two 80” motor leads through the hanger ball and
slide the hanger ball over the downrod.
Position the pin through the two holes in the downrod and
align the hanger ball so the pin is captured in the groove in
the top of the hanger ball.
Pull the hanger ball up tight against the pin and securely
tighten the set screw in the hanger ball. A loose set screw
could create fan wobble.
3. Ceiling Fan Assembly (Continued)
It is critical that the pin in the hanger ball is properly
installed and the set screw securely tightened. Failure to
verify that the pin and set screw are properly installed
could result in the fan falling.
WARNING
!