44 Solution 2.3 Installation and Operation Manual
Appendix 1: Installing the Legs or Pedestal
The leg or pedestal kit must be assembled to the firebox before positioning the stove. See
installation instructions below:
1- Remove the firebricks, the ash dump plug
and the loading door from the stove to
avoid breaking any parts and facilitate
handling in the followings steps.
2- Gently flip the stove on its back.
3- Remove the (2) transport support bracket
which can be discarded. Keep the (4)
bolts, washers and nuts since they will be
required in step 5.