Ensemble Commissioning: Installer Toolkit Communications
© 2020 Enphase Energy Inc. All rights reserved. July 24, 2020
___________Installer Initials: All steps complete on this page
10
H.3.6. Wait 60-330 seconds for the microgrid interconnect device relay to close.
H.3.7. Allow Encharge LEDs to flash red.
H.3.8. Turn ON DC switches on all Encharges. The Encharge LEDs should stop
flashing red after DC switches are turned ON.
I. Once you confirm that Encharge batteries are communicating with Envoy, you must update
the Encharge firmware. This process takes several hours and can be completed overnight
following installation. The following screenshots show how to initiate this update and show the
status screen that communicates progress of the update.
J. Installer Toolkit step 6, Configure Production and Consumption CTs using the meter
wizard:
J.1. Verify that the configuration matches what is installed (solar + load or load only).
J.2. Enable the meters by verifying the readings manually or go
through the meter wizard (recommended).
J.3. While in the production meter wizard, switch OFF the PV
breakers as instructed to make sure the readings go to zero
before enabling.
J.4. While in the consumption meter wizard, turn ON the PV and
a known load in the home to confirm consumption rises as
expected, and select the meter location (solar + load)
J.5. Once the meters are configured correctly, you will be able to
see if the Encharge batteries are charging or discharging in
the devices section of Installer Toolkit.
K. Installer Toolkit step 7, Generate a Summary Report: