MAITENANCE & INSPECTION
The maintenance and inspection should be carried out only after the switches
in the switch box are certainly turned OFF.
Try to maintain and inspect the set regularly as per the following guidelines.
a) Regular Inspection
Every 3-6 months, depending on operation frequency:
b) Cautions to Insulation Voltage – Proof Test & Insulation
Resistance Measurement Test:
Careless execution of Dielectric Strength test and Insulation
Resistance Measurement will cause damage to the Power Source
since diodes and other semiconductor parts are widely used in the
unit. When these are to be performed in accordance with the bylaws
of your company, the following points should be kept in mind :
• Remove input cable from main supply and short-circuit the three
input terminals.
• Take off the cable that is connected to two output terminals
and short-circuit the two output terminals.
• Short-circuit the diode block.
• Remove the three grounding conductors. (Take off the top cover,
the remove two grounding conductors – one near the control
transformer, another near the electromagnetic contractor. Take
off the right side panel, and remove the grounding conductor
near the leg of the main transformer).
• Disconnect the Wirefeeder from the Power Source.
10