C-12 CRUSHER
PREPARING THE CRUSHER FOR OPERATION Cont.
10:- Remove side conveyor locking pin
11:- Activate lever marked "Side Con Fold" to lower
side conveyor.
Side conveyor in working position
12b:- Fix main conv. spray bar in working position.12a:- Raise main conv. spray bar to working
position.
Locking Pin
9:- Fit & tighten bolts at hopper leg/chassis. (Both
sides)