C-12 CRUSHER
PREPARING THE CRUSHER FOR OPERATION Cont.
13a:- Locate safety gate in holes in RH side walkway.
15:- Fit pins & R-clips to jack legs (8 off)
WARNING:- a) Ensure the machine is on a level surface before operating the jack leg levers.
b) Lift the machine uniformly.
13b:- Push safety gate firmly down into holes.
13c:- Raise up rotating gate section. (NOTE:- while
operator is using the platforms the safety gates
MUST be closed).
13d:- Rotate & lower gate into position. Repeat
procedure on other side of machine.
14:- Lower jack legs by operating levers.