H0.1 Manoeuvres to unfold the crane into a working condition
- Engage the power take off.
- Stabilize the vehicle (see details on Paragraph G2 “Manoeuvres and controls
to stabilize the vehicle”).
(!) IT IS FORBIDDEN TO OPERATE FROM (!)
THE DOUBLE CONTROL SIDE
(!) Operate from ground control distributor side (!)
By operating the corresponding levers:
- make sure that the extension booms and the outer ram are closed;
- lift the inner boom over the horizontal line;
- open the outer boom to the “horizontal” position;
- position the hook on the vertical line above the load.
H0.2 Manoeuvres to fold the crane into the
rest condition
(!) IT IS FORBIDDEN TO OPERATE FROM (!)
THE DOUBLE CONTROL SIDE
(!) Operate from ground control distributor side (!)
By operating the corresponding levers:
- fold the extension booms to their stroke end;
- lift the inner boom to its stroke end;
- fold the outer boom to its stroke end;
- rotate the crane until the reference arrows coincide (on the column and on the base);
- fold the inner boom to its stroke end; the rest locating pin locates into its seat;
- re-position the outriggers to within the overall vehicle width as described on
Paragraph G2.
NOTE A safety device is installed on the outer boom of the crane version "C"
preventing the exit of the extension boom sections when the crane is
in rest position.
H0.3 Manoeuvres to unfold the crane "C" into a working
condition
(!) IT IS FORBIDDEN TO OPERATE FROM THE DOUBLE CONTROL SIDE (!)
(!) Operate from ground control distributor side (!)
- Lift the inner boom over the horizontal line.
- Open the outer boom to the “horizontal” position.
- Extend the extension boom sections; the hook of the safety device is free.
- Position the hook on the vertical line above the load.
H0.4 Manoeuvres to fold the crane "C" into the rest condition
(!) IT IS FORBIDDEN TO OPERATE FROM THE DOUBLE CONTROL SIDE (!)
(!) Operate from ground control distributor side (!)
By operating the corresponding levers:
- lift the inner boom close to its stroke end;
- fold the outer boom to its stroke end;
- lower the inner boom until the hook of the safety device rests on the extension
boom sections;
- reenter the extension booms sections to engage the hook and keep the
extension boom sections in place;
- do not insist on the control!
- rotate the crane until the reference arrows coincide (on the column and on the base);
- fold the inner boom to its stroke end; the rest locating pin locates into its seat;
- re-position the outriggers to within the overall vehicle width as described on
Paragraph G2
H0.1
CONTROLS TO
OPERATE THE CRANE
F 170A
23