En-33
TEST RUN9. 2.
Pre-test run check items9. 2. 1.
Beforethetestrun,refertothegureandcheckthefollowingitems.
1
Is check run performed? Test run doesn't operate if check run is not performed. (“FAIL” is displayed when
operating the unit before the check run is done.)
After checking that the above items are all in order, refer to “9.2.2. Test run method” to test
run the unit.
If there are problems, adjust immediately and recheck.
Test run method9. 2. 2.
Besuretoconguretestrunsettingsonlywhentheoutdoorunithasstoppedoperating.
Depending on the communication status between the indoor and outdoor units, it may take several minutes for
the system to start operating after settings for the test run are complete.
After the test run settings are complete, all the outdoor units and the connected indoor units will start operating.
Room temperature control will not activate during test run (continuous operation).
Test run set with the outdoor unit doesn't stop automatically. Be sure to stop the operation according to the
operation method.
All indoor units will operate when test run is performed from the outdoor unit. At this time, the remote controller of
the indoor unit is unavailable.
Operation mode cannot be changed during the test run. To change the operation mode, please stop the test run
rst,andthenperformthetestrunagain.Atthistime,thecompressorcannotberestartedfor3minutesafterit
stops in order to protect the indoor unit. Please restart it after 3 minutes.
9379069342-02_IM.indb 33 17/5/2556 11:50:01