4. Place the branch pipe in a horizontal position as far as possible.
a. Only place the branch pipe as shown below during unavoidable circumstances.
Horizontal
position
b. When connecting the main piping, do not bend it near the connection section. If the main
pipe must be bent due to unavoidable circumstances, ensure that the linear section is 10
times or more than the diameter of the connection piping.
Main pipe
Straight pipe =
(D x 10) and above
to indoor unit
Ø
D
R
to outdoor unit
to indoor unit
5. Welding the piping
Check that the connection piping is securely inserted into the branch pipe before welding.
CAUTION
During piping work, apply nitrogen gas while brazing the pipes. If pipes are brazed without ap-
plying nitrogen gas, it will create a large amount of oxidation film, which will cause a critical
malfunction.
To prevent moisture or foreign matter from entering during work, do not leave the piping open.
Refer to installation manual supplied with the outdoor unit for sealing test evacuation proce-
dures.
- 109 -