INSTALLATION OF THE ELECTRICAL GENERATOR
4.1 .- UNLOADING AND TRANSPORT
The unloading and transport of the unit should only be done by qualified personnel, observing certain minimum
safety conditions.
The ground must be capable of supporting the full weight of the Generator and the forklift.
Make sure that the battery is disconnected.
Make sure that the fuel tank is empty.
Place the open arms of the forklift below the chassis at an equal distance with respect to the lifting frame.
With a hoist, raise the unit using the lifting frame eyebolt.
The image below shows a generator unit that which includes a frame with a single lifting point.
Image 9 - LIFTING FRAME