INSTALLATION OF THE ELECTRICAL GENERATOR
4.1 .- UNLOADING AND TRANSPORT
The unloading and transport of the unit should only be done by qualified personnel, observing certain minimum
safety conditions.
• The ground must be capable of supporting the full weight of the Generator and the forklift.
• Make sure that the battery is disconnected.
• Make sure that the fuel tank is empty.
•
Place the open arms of the forklift below the chassis at an equal distance with respect to the lifting frame.
• With a hoist, raise the unit using the lifting frame eyebolt.
The image below shows a generator unit that which includes a frame with a single lifting point.
Image 9 - LIFTING FRAME