9. Branch pipes should be connected to the top of a horizontal main
pipe.
10. A steam sampling point with shutoff valve should be provided
between the reducing valve and the sterilizer so that the quality of
the steam can be checked. The sampling point can also be used for
blow-down in preparation for work that requires the steam system
to be depressurized.
11. Because it is intended to be used daily, the shut off valve should be
easy to operate, for instance a remote controlled ball valve.
12. Insulate steam pipes up to the sterilizer steam connection.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Getinge GE 6610 AC-1 and is the answer not in the manual?

Getinge GE 6610 AC-1 Specifications

General IconGeneral
BrandGetinge
ModelGE 6610 AC-1
CategoryLaboratory Equipment
LanguageEnglish

Related product manuals