Step 0 - Site Selecon and Ground Pole Installaon
A site with a clear, unobstructed view is preferred. Also consider obstrucon that may occur in the
future such as the growth of trees.
>See secon 4.0 for more details.
2.0 ASSEMBLY AND INSTALLATION
5/2
3
Step 1 - Aach AzEl to Back Bracket
1. From inside the Back Bracket, align the ve hole
paern on the Az/El.
2. Feed the (5) 5/16 x 3/4” RHSN bolts (Item 5/1)
from the back bracket to the Az/El.
3. Secure with (5) 5/16 hex ange nuts (Item 5/2).
Torque to a maximum of 15 /lbs.
5/1
Step 2 - Install Antenna on Mounng Pipe
1. Before aaching the Antenna system to the
mounng pipe use a magnec level to verify the
horizontal and vercal level of the pipe.
2. Being aware of health & safety at all mes, Carry
the Antenna to the pipe.
3. Slide the tube canister of the Az/El Assembly
(Item 3) over the top of the pipe and lower into
place.
4. Secure in place at this stage by hand ghtening
the 5/16” ange nuts on the canister assembly.