13503
7.1 Hanging Bracket Fixing
If previously removed, reposition the wall template over the
flue hole and mark the position of the fixing holes for the
hanging bracket, see diagram 7.1.
Mark and drill the fixing holes and secure the hanging bracket
which is supplied in the polystyrene base pack.
NOTE: Due to the varied site conditions we do not supply
fixings and advise that the installer should supply those
which are suitable.
7.2 Boiler Hanging
IMPORTANT: With regards to the Manual Handling
Operations, 1992 Regulations, the following lift operation
exceeds the recommended weight for a one man lift, refer to
section 17 Manual Handling.
Lifting the boiler into position, lean the top of the boiler
slightly to the wall and position just above the hanging
bracket. Lower the boiler slowly and engage onto the
hanging bracket, see diagram 7.2.
Remove the polystyrene base support.