EasyManua.ls Logo

Goodman GMV series - Page 76

Goodman GMV series
131 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
PRODUCT DESIGN
76
FAN ONLY MODE
The normal operational sequence in fan only mode is as
follows:
1. R and G thermostat contacts close, initiating a call for
fan.
2. Integrated control module performs safety circuit checks.
3. Circulator blower is energized on continuous fan speed
(56% of high stage cooling) following a five (5) second
delay. Electronic air cleaner terminals are energized.
4. Circulator blower runs, integrated control module moni-
tors safety circuits continuously.
5. R and G thermostat contacts open, completing the call
for fan.
6. Circulator blower is de-energized. Electronic air cleaner
terminals are de-energized.
7. Furnace awaits next call from thermostat.
DEHUMIDIFICATION M ODE
The normal operational sequence in dehumidification
mode is as follows:
1. R and YLO/G or Y/G thermostat contacts close, initiaing
a call for cool.
2. Integrated control module performs safety circuit checks.
3. Outdoor fan and compressor are energized to their ap-
propriate speed.
4. Circulator blower is energized on the appropriate cool
speed at the level and time determined by the selected
ramping profile. Electronic air cleaner terminals are en-
ergized with circulator blower.
5. Furnace circulator blower and outdoor cooling unit run
their appropriate speed, integrated control module moni-
tors safety circuits continuously.
6. Dehumidistat opens on humidity rise allowing the fur-
nace circulator blower to operate at 80% of the cooling
speed during combined thermostat call for cooling and
dehumidistat call for dehumidification.
7. Humidistat opens on humidity fall allowing furnace cir-
culator blower to switch back to normal cooling speed.
8. R and YLO/G or Y/G thermostat contacts open, com-
pleting the call for cool.
9. Outdoor fan and compressor are de-energized.
10. Circulator blower continues running during a cool off
delay period. The OFF delay time and airflow level are
determined by the selected ramping profile.
11. Electronic air cleaner terminals and circulator blower
are de-energized.
12. Furnace awaits next call from thermostat.

Related product manuals