OPERATION MANUAL - Trailer Refrigeration Unit
arktik 1600N • 1600 N/T • 2000N • 2500N • 2000P • 2500 N/K • 2000 P/K
50.04.504 / 1.0
Copyright by GOVI GmbH 2021. The reproduction of this document or any part thereof is prohibited. We reserve the right to make technical changes during the course of further developments.
18
Page
6.3.1 General Preparation
1. Place the refrigerated trailer and trailer refrigeration unit side by side
on a dry and clean level ground.
2. Verify that the trailer is in horizontal position.
3. Make sure that the contact area between its front wall and the trailer
refrigeration unit is free from impurities
4. Remove all obstacles from the installation area.
5. Prepare all required tools and equipment and place them in a safe
place easily accessible from the installation area.
6. Verify that the PU seal (1) at the backside of the trailer refrigeration
unit is available and intact.
1
6.3 Preparatory Activities
Fig. 6-1 PU seal of the
trailer refrigeration unit
1. PU-Seal