GREE GMV5E DC INVERTER VRF UNITS SERVICE MANUAL
115
Click "Start" to enter the commissioning function and the software automatically performs
commissioning. " " indicates that commissioning is being performed on the phase and " "
indicates that commissioning is passed on the phase.
For the phase with "OK" displayed, a manual confirmation is required for entering the next
commissioning step. Click " " to display relevant information detected on this phase, which provides
references for selection. Click "Close" to close the information (the number of commissioning units is
displayed in "3 Confirm ODU Basic Module NO." and "4 Confirm IDU NO."; the preheating period is
displayed in 8 Compr. Preheat Confirmation").