Ultra Heat GMV5 User Manual
11
Fig. 9
Rated capacity of IDU
C(Btu/h)
NOTICE! If the distance between IDU and its nearest branch is over 10m(33feet), then the
liquid pipe of IDU (rated capacity ≤17000Btu/h) shall be enlarged.
4.3 Installation of Connection Pipe
(1) Conform to the following principles during pipe connection: Connection pipe should be as short as possible, so
is the height difference between indoor and outdoor units. Keep the number of bends as little as possible.
Radius of curvature should be as large as possible.
(2) Weld the connection pipe between indoor and outdoor units. Please strictly follow the requirements for welding
process. Rosin joint or pin hole is not allowed.
(3) When laying the pipe, be careful not to distort it. Radius of bending parts should be over 200mm(8inch). Note
that pipes cannot be repeatedly bent or stretched; otherwise the material will get harder. Do not bend or stretch
the pipe for more than 3 times at the same position.
4.3.1 Flaring Process
(1) Use pipe cutter to cut the connection pipe in case it is unshaped.
(2) Keep the pipe downward in case cutting scraps get into the pipe. Clear away the burrs
after cutting.