GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 
119 
 
" " indicates that commissioning is not passed on the phase and troubleshooting is required (after 
troubleshooting, the unit automatically enters the next step if no "OK" exists or click "OK" to enter the 
next step). Click " " to display relevant information detected on this phase, which provides references 
for troubleshooting. Click "Close" to close the information. 
 
During  commissioning,  click  "Stop"  to  stop  commissioning  and  then  click  "Start"  to  continue 
commissioning  till  commissioning  ends.  "Back"  and  "Skip"  are  provided  in  "10  ODU  Valves  Check 
Before Startup". When an exception occurs in step 10, click "Back" to return to step 9 and then click "OK" 
in step 9 to perform commissioning again for step 10. If a U6 fault (valve exception) occurs in step 10, 
users can click "Skip" to skip the fault. For other faults, "Skip" is unavailable.