GMV5 DC INVERTER VRF UNITS SERVICE MANUAL
213
5. Install a new oil
separator.
Weld the four pipe joints with
the oil separator.
During welding, charge nitrogen
into the pipes. The pressure
should be controlled within
0.5±0.1 kgf/cm2 (relative
pressure).
Note: Avoid nearby parts from
being burnt during welding.
●Screw the oil separator.
Tighten the electric heating
belt.
6. Fix and wire the
electric box.
●Put the electric box back to
original position and screw it.
Connect all lines.
7. Check and install
the front panels.
●Check various parts and
connecting lines.
If no problem is found, hook
the front panels and tighten the
screws.
Gas/liquid separator
Precondition: No refrigerant exists in the pipeline system and the power supply has been disconnected.
Step
Diagram
Operation Procedure
1. Loosen the hooks
at the bottom of the
electric box and the
screws.
Remove the upper and lower
front panels.
Loosen the hooks at the
bottom of the electric box.
Use a screwdriver to unscrew
the electric box.

Table of Contents

Other manuals for Gree GMV-615WM/B-X

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Gree GMV-615WM/B-X and is the answer not in the manual?

Gree GMV-615WM/B-X Specifications

General IconGeneral
BrandGree
ModelGMV-615WM/B-X
CategoryAir Conditioner
LanguageEnglish

Related product manuals