EasyManua.ls Logo

Gree GMV-615WM/G-X

Gree GMV-615WM/G-X
305 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Gree GMV6 DC Inverter VRF Units Service Manual
37
Note:
During commissioning, users must listen to the operating sound of outdoor and indoor fans and
compressors to check for exceptions.
3.2.5 Unit Commissioning by Using Multi-functional Debugger
Step 1:
Connect multi-functional debugger. For details, see the user manual of multi-functional
debugger.
Step 2:
Set the address DIP switch (SA8) of the master outdoor unit to 00. Otherwise, it is invalid.
Step 3:
Click
Unit Debug
on the home page to enter the commissioning page.
Step 4:
On the commissioning page, click
Startup
to start commissioning or click
Stoppage
to stop
commissioning.

Other manuals for Gree GMV-615WM/G-X

Related product manuals