Chapter Maintenance3. Maintenance of Key Parts
68
2 Remove
the nuts fixing the
compressor
footing.
Compressor
Nut
● Use bending bar or other
tools to unfasten the
compressor fixing nuts.
3Cut off the
pipes from the
compressor.
When using a soldering gun,
weld the pipes quickly to
prevent pipeline from
overburning;
● In order to guarantee
compressor replacement and
for furture disassembly
analysis, do not damage the
compressor.
4 Remove
the compressor
from the base
plate and locate a
new compressor
onto the
baseplate.
When removing the
compressor, be careful not to
damage compressor‟s rubber
grommet;
The replaced compressor
should be well sealed to
prevent water from getting in;
Place the newly replaced
compressor onto the rubber
grommets. Wear steel bushing
on the center of the grommet;
Tighten up the nuts to the
position of steel bushing.
5 Connect
the suction port
and discharge port
of compressor to
the system
pipeline. Connect
power cord and
check whether the
compressor can
run normally.
Connect the suction and
discharge pipeline to the
compressor by welding. Fill
nitrogen for the welding;
After welding, it is required
to fill high pressure nitrogen to
conduct leak test;
Power on the unit and
energize the AC contactor of
the compressor manually to
turn compressor on for 2~3
seconds;
If compressor is reversed,
ear-piercing noise will occur.