2) Refer to quick installation guidance, complete the installation and wire connection. Ensure
PACK in off status during all the steps.
3) Set the power system as “CC≤25A, CV=55.8V” , activate the PACK and start recharging.
4) Recharge until LED2 flicks.
5) Having completed recharge, leave circuit open for five minutes before check voltage. If
voltage is not less than 52V, the recharge succe.
3.2 Transportation Requirement
PACK has been certified in UN38.3 (Section 38.3 of the sixth Revised Edition of the
Recommendations on the Transport of Dangerous Goods: Manual of Tests and Criteria) and SN/T
0370.2-2009 (Part 2: Performance Test of the Rules for the Inspection of Packaging for Exporting
Dangerous Goods). PACK is classified as category 9 dangerous goods.
The PACK shall not be transported with other inflammable, explosive or toxic substances
Ensure the original Package and label complete and recognizable.
Prohibit direct exposure to sunlight, rain, condensing water caused by temperature difference and
mechanical damages.
There will be a drop in capacity during transportation and storage.
Transportation temperature is between-20°C to 45°C, relative humidity: 5%~95%RH
4 Installation
Ensure to read the Guidance before installation in order to understand product information and safety
cautions;
Operators should be well trained technicians and fully understand the whole photovoltaic system, grid
network, working principle and national regional standards;
Installers must use insulating tools and wear safety equipment;
Device damages caused by failure to comply with storage, transportation, installation and use
requirements specified in Guidance are not coved by Warranty.
The PACK can only be installed indoors. Regarding indoor installation, please do not install it in the
bedroom, living room, kitchen, etc.
Different types of batteries are not recommended to be mixed and used in parallel. For example, AXE
5.0L-C1 cannot be mixed with AXE 5.0L-P1.
The battery system cannot be installed, dismantled, and maintained when it has been powered on.
4.1 Installation environment
The ambient temperature for the installation of the battery system shall be above 0℃, below 50℃, and
the humidity shall between 5% and 95%.