volt higher, thus is 265 volt.
(3) Then click “Operate” to apply the change. Once inverter accepted, it would show “Set
OK” in “Set Result” filed.
(4) Tick the “Read” checkbox, and click “Operate” to read and check the change.
After BOTH of the above adjustment had been done successfully (For new version inverters
installed after 9, October, 2016), please switch ON the AC switch to start up inverter.
1.3 PV Isolation Low
Cause: Insulation problem.
Inspection procedure of insulation problem on site:
Check the earth wiring on AC side, check the isolation on DC side (PV side).
1. Check if the inverter’s AC side is well grounded,
2. Switch off the DC isolator, unplug the DC connectors, test the positive to earth and
negative to earth voltage or resistance on the DC MC4 plugs. If the voltage is not 0, please
check the earth wire of the solar panels.
3. Turn on the DC switch to measure the voltage of DC positive to ground and the voltage of
DC negative to ground. The reading will be 0 under normal condition, if the voltage is not 0,
you can locate the fault area by dividing the voltage by Voc of PV solar module, as a panel
with Voc=21v , if the test indicate that the Positive to ground voltage is 42V, Negative to
ground voltage is 63V, then the fault is located between the 2 and 3 panels from positive
side.