14
To summarize
Before fitting the A/H:
1. Install copper pipework
2. Fit the drain
3. Provide the power supply (GPO)
Now fit the A/H with the sub frame into the cupboard.
4. Screw the subframe into the cupboard front panel
5. Connect the drain (pp 9)
6. Connect up the refrigeration pipes (pp 8 & 9)
7. Open up the refrigeration circuit (pp 13)
8. Leak test (pp 15)
9. Install facia (pp 7)
10. Test (pp 19).
Figure 14