OPERATIONS TO BE PERFORMED ONCE THE ACTIVITY HAS BEEN COMPLETED | PAGE 17
5. OPERATIONS TO BE PERFORMED ONCE THE
ACTIVITY HAS BEEN COMPLETED
5.1 SWITCHING OFF THE SPOTLIGHTS
Switch off the spotlights switches and stop the gen-set (see control unit manual).
CUADRO MANUAL PARA TORRE DE ILUMINACION
ESQUEMA ELÉCTRICO DE CONTROL "M7"
Y PROTECCIÓN MAGNETOTÉRMICA
LIGHTING TOWER MANUAL START CONTROL PANEL
"M7" CONTROL AND THERMAL MAGNETIC
PROTECTION ELECTRIC DIAGRAM
DE 10 AMPERIOS
FROM 10 AMPERES
*WARNING*
MAKE SURE ALL THE POWER UNITS ARE OFF
BEFORE START THE GENSET!!
www.himoinsa.com
1 2 3 54 76 8 9 10 1211 1413 15 16
Telf. 968 191 128
APPROVED:
OLD CODE:
NEW CODE:
DESIGN:
REVISED/
NAME:
DATE:
SIGNATURE
DESCRIPATION:
Nº P.:
REVISION:
SCALE:
CODE:
CTRA.MURCIA-SAN JAVIER KM 23.600 C.P. 30730 - MURCIA - ESPAÑA
1/17/2014
1/17/2014
mm
03
Miguel Utrillas
CCAC16AB20002-R0
Fig.1
5.2 LOWERING THE MAST
We advise you to wait between 20-25 minutes before lowering the tower. Due to the
high temperatures that the laments of the spotlights reach, they are very vulnerable
to the slight vibrations that inevitably occur when the mast is being lowered.
• Press the down button installed on the control panel
Fig.2