Units installation
13.3 INSTALLATION PLACE PROVISION
13
1  Secure the outdoor unit with the anchor
Max 17mm
Concrete
Filled mortar
Anchor bolts
Special 
washer 
(M12)
Nut
Base of  
outdoor unit
Fix the outdoor unit to the anchor bolts by special washer of fac-
tory-supplied accessory.
2  When installing the outdoor unit, x the unit by anchor bolts. 
Regarding the location of xing holes.
Front side
Pipe cover
M10 Hole for anchor bolt (Ø 12)
3  Example of xing outdoor unit by anchor bolts.
A
Concrete
Anchor bolt
Cut this portion when 
this type of anchor 
bolt is used. If not, it 
is dicult to remove 
the service cover
4  Provide an adequate drainage around the foundation. When 
installing  the  unit  on  a  roof  or  a  veranda,  drain  water  may 
turn to ice in a cold morning. Therefore, avoid draining in an 
area where people often use because it is slippery. In case of 
installing such a place, provide the additional drainage around 
the foundation.
(30x80)
(30x80)
76
339
147
(228)
4-R8
58
40
42
Drain hole
Drain hole 
Position for drain 
boss (optional)
Drain hole
Front side
5  The whole of the base of the outdoor unit should be installed 
on  a  foundation.  When  using  vibration-proof  mat,  it  should 
also be positioned the same way. When installing the outdoor 
unit on a eld supplied frame, use metal plates to adjust the 
frame width for stable installation as shown in gure.
INCORRECT
57mm 
Base width of 
outdoor unit
Outdoor unit 
is unstable
60mm 
Frame width  
(eld supplied)
Frame
CORRECT
Outdoor unit 
is stable
57mm 
Base width of 
outdoor unit
100mm or more 
Metal plate
Metal plate
Frame
Recommended metal plate size (eld-supplied)
 - Material: Hot-rolled mild steel plate (SPHC)
 - Plate thickness: 4.5T