18
Dip switch setting Operation Remarks
Test run
 Setting of operation mode.
Cooling: Set DSW301 pin 1-2 OFF. 
Heating: Set DSW301 pin 2 ON. 
 Starting  test  run.  Set  DSW301 pin  1 
ON  and  the  operation  is  started  after  a 
few ~20 seconds.
Cooling Heating
 The indoor unit automatically start to 
operate when the test run of the outdo-
or unit is set.
 The ON/OFF operation can be per-
formed from the remote control switch 
or DSW301-1 of the outdoor unit.
 Continuous operation during 2 hours 
is performed without Thermo-OFF.
 NOTE
TEST RUN operation time can be in-
creased depressing the time switch 
in the Remote Control.
If is setting DSW1-3 ON, cooling/
heating intermediate season mode is 
activaded.
Take care that the indoor units start opera-
tion in accord with the test run operation of 
the outdoor unit.
If the test run is started from the outdoor 
unit, cannot be cancelled by the remote 
control.
In case that the plural indoor units are 
connected with one remote control switch, 
all the units start test run operation at the 
same time, therefore, turn the power sour-
ce OFF for the indoor units not to operate 
test run. In this case, the TEST RUN in-
dication of the remote control switch may 
icker, and this is not abnormal.
The setting of DSW1 is not required for the 
test run from the remote control switch.
Manual OFF of 
compressor
 Setting
- Compressor Manual OFF:
Set DSW301 pin 4 ON.
- Compressor ON:
Set DSW301 all pins OFF.
 When DSW301-4 is ON during com-
pressor operation, the compressor stops 
to  operate  immediately  and  the  indoor 
unit  is  under  the  condition  of  Thermo-
OFF.
 When DSW1-4 is OFF, the compres-
sor starts to operate after the cancella-
tion of 3-minutes guard.
•  Do not repeat compressor ON/OFF fre-
quently.
Manual defrost
 Manual defrost operation starts. Press 
PSW1  for  more  than  3  seconds  during 
heating  operation,  the  defrost  operation 
is started after 2 minutes. This function is 
not available within 5 minutes after star-
ting heating operation.
  Manual  defrost  operation  nishes. 
Defrost operation is automatically ended 
and the heating operation is started.
 Defrost  operation  is available  regar-
dless of frosting condition and total time 
of heating operation.
  Defrost  operation  in  not  performed 
when  the  temperature  of  outdoor  heat 
exchanger  is  higher  than  10°C,  high 
pressure is higher than 3.3MPa (33kgf/
cm
2
G) or Thermo-OFF.
•  Do  not  repeat  defrost  operation  fre-
quently.